May marked another exciting milestone for the project as steel erection began in the kindergarten wing. Progress also continued on the west side of the classroom wing, where block walls are steadily rising. Concrete crews remained hard at work forming and pouring sections of the site retaining wall and courtyard seating areas. On the main building pad, foundation work has been completed, and foundation block is being laid around the stage. In addition, the site water and fire lines have been installed around the building and continue towards Compton Rd.