March marked continued momentum across the site, as this phase of sitework concluded with the completion of the detention pond excavation and installation of sanitary piping along the west side. Concrete crews continued forming and pouring the retaining wall, defining the separation between key building areas. Foundations for the future classroom wing advanced, with block work following closely behind. Underground plumbing also began beneath the kindergarten restrooms, marking another step forward in bringing this space to life!