Another major milestone was reached this month as both concrete floor slabs were poured in the lower level of the classroom wing. In the kindergarten area, bearing block walls have now risen over 10 feet high, setting the stage for structural steel arriving in late May / early June.
Concrete crews continued progress on forming and pouring sections of the retaining wall, allowing waterproofing and backfilling to begin. On the main building pad, construction has begun on the kitchen and stage foundations, with underground plumbing close behind.